Live Construction Updates

Construction Milestone

Building Dreams, Delivering Quality

2nd Floor Completed • 3rd Floor Slab Work in Progress • Expected Possession: Feb 2027

Overall Progress
45%

Target completion: February 2027

2/7
Floors Done
45%
Structure
Soon
Finishing
3rd Floor
Slab
Current Phase
Construction Timeline

Phase by Phase Progress

Foundation & Plinth

Completed

Raft foundation with UltraTech cement. Anti-termite treatment done.

✓ March 2024

Ground Floor Slab

Completed

RCC columns, beams and slab work completed. Quality checked.

✓ August 2024

1st Floor Slab

Completed

Full structural work done. Brick masonry in progress on ground floor.

✓ November 2024

2nd Floor Slab

Completed

2nd floor structure fully complete. Electrical conduit work initiated.

✓ February 2025

3rd Floor Slab

In Progress

Shuttering placed. Concrete pouring scheduled. Steel reinforcement done.

⟳ Est. completion: May 2025

65% done

4th – 7th Floor

Upcoming

Floors 4 through 7 — structure, masonry, plumbing & electrical.

Est. Jun 2025 – Sep 2026

Finishing & Handover

Upcoming

Flooring, painting, Jaquar fittings, Asian Paints finish, lift installation.

Est. Oct 2026 – Feb 2027

Site Photos

Live from the Construction Site

Site Photo 1
Site Photo 2
Site Photo 3
Site Photo 4

Want to Visit the Construction Site?

See the quality of construction firsthand. Book a guided site visit today.